Integrating RII, VSM, and EVM to Optimize Construction Performance of a Physiotherapy Facility in a Remote Mining Area
DOI:
https://doi.org/10.59261/jequi.v8i5.471Keywords:
Relative Importance Index, Value Stream Mapping, Earned Value Management, EPC projectsAbstract
Background: Construction projects in remote mining areas face schedule disruptions caused by complex approval procedures, logistical constraints, and changing project requirements. An integrated assessment is needed to identify the underlying causes of delays, their operational impacts, and their consequences for project performance.
Objective: This study aims to integrate the Relative Importance Index (RII), Value Stream Mapping (VSM), and Earned Value Management (EVM) to assess construction performance in a physiotherapy facility renovation project.
Methods: A single-case study was conducted using questionnaires completed by 30 respondents, interviews with 10 key informants, observations of 19 activities, project progress reports covering 34 weeks, and project documentation. RII was used to prioritize delay factors, VSM to identify operational waste, and EVM to evaluate schedule performance.
Results: The dominant delay factors were approval delays (RII = 0.947), logistical constraints (RII = 0.920), and scope changes (RII = 0.900). VSM identified 217 activity-days of cycle time and 292 activity-days of waiting time, yielding a total of 509 activity-days and a value-added ratio of 36.94%. The proposed future-state scenario indicated a potential reduction of 128 activity-days, although this estimate requires empirical verification. EVM yielded Schedule Performance Index (SPI) values of 0.773, 0.847, and 0.970 in Weeks 14, 27, and 34, respectively.
Conclusion: Integrating RII, VSM, and EVM provides a traceable framework for prioritizing delay factors, identifying process bottlenecks, and assessing schedule deviations. The proposed improvements require post-implementation validation before their effectiveness can be confirmed.
Downloads
References
Anggraini, W., Harpito, Siska, M., & Novitri, D. (2022). Implementation of Lean Construction to Eliminate Waste: A Case Study Construction Project in Indonesia. Jurnal Teknik Industri, 23(1), 1–16. https://doi.org/10.22219/JTIUMM.Vol23.No1.1-16
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Bajjou, M. S., & Chafi, A. (2018). Lean construction implementation in the Moroccan construction industry. Journal of Engineering, Design and Technology, 16(4), 533–556. https://doi.org/10.1108/JEDT-02-2018-0031
Deng, J., & Jian, W. (2022). Estimating construction project duration and costs upon completion using Monte Carlo simulations and improved earned value management. Buildings, 12(12), 2173. https://doi.org/10.3390/buildings12122173
Durdyev, S., & Hosseini, M. R. (2019). Causes of delays on construction projects: a comprehensive list. International Journal of Managing Projects in Business, 13(1), 20–46. https://doi.org/10.1108/IJMPB-09-2018-0178
Elsaid, M., Nassar, K., Alqahtani, F. K., & Abotaleb, I. (2025). Comparative analysis of earned value management techniques in construction projects. Scientific Reports, 15(1), 23606. https://doi.org/10.1038/s41598-025-05834-z
Hines, P., & Rich, N. (1997). The seven value stream mapping tools. International Journal of Operations & Production Management, 17(1), 46–64. https://doi.org/10.1108/01443579710157989
Intifada, W. (2012). Meminimasi Waste Menggunakan Value Stream Analysis Tool Untuk Meningkatkan Efisensi Waktu Produksi. Jurnal Teknik Pomits .
Kadry, M., Osman, H., & Georgy, M. (2017). Causes of Construction Delays in Countries with High Geopolitical Risks. Journal of Construction Engineering and Management, 143(2). https://doi.org/10.1061/(asce)co.1943-7862.0001222
Kim, Y., Lee, D., & Park, D. (2022). A Case Study on BIM Object-Based Earned Value and Process Management in Highway Construction. KSCE Journal of Civil Engineering, 26(2), 522–538. https://doi.org/10.1007/s12205-021-1348-3
Koskela, L. (1992). Application of the new production philosophy to construction. Center for Integrated Facility Engineering.
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome. International Journal of Project Management, 27(4), 400–407. https://doi.org/10.1016/j.ijproman.2008.02.009
Mike Rother, J. S. (1999). Learning to see - value stream mapping to add value anda eliminate muda. The Lean Enterprise Institute.
Morato, M. L. de S., & Ferreira, K. A. (2024). Value stream mapping application for construction industry loss and waste reduction: a systematic literature review. International Journal of Lean Six Sigma, 15(4), 817–837. https://doi.org/10.1108/IJLSS-06-2023-0100
Oyewobi, L. O., Okanlawon, T. T., Ogunjimi, O. S., & Jimoh, R. A. (2025). Lean construction management: stationary analysis of the barriers to the implementation of value stream mapping (VSM) in achieving sustainable construction project. International Journal of Lean Six Sigma, 16(7), 1612–1640. https://doi.org/10.1108/IJLSS-09-2024-0210
Proaño-Narváez, M., Flores-Vázquez, C., Vásquez Quiroz, P., & Avila-Calle, M. (2022). Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections. Buildings, 12(3), 301. https://doi.org/10.3390/buildings12030301
Project Management Institute. (2019). The standard for earned value management. Project Management Institute.
Purushothaman, M. B., San Pedro, L. N. R., & GhaffarianHoseini, A. (2026). Construction projects: interactions of the causes of delays. In Smart and Sustainable Built Environment (Vol. 15, Number 2). https://doi.org/10.1108/SASBE-11-2023-0334
Ramani, P. V., & KSD, L. K. L. (2021). Application of lean in construction using value stream mapping. Engineering, Construction and Architectural Management, 28(1), 216–228. https://doi.org/10.1108/ECAM-12-2018-0572
Shou, W., Wang, J., Wu, P., Wang, X., & Chong, H.-Y. (2017). A cross-sector review on the use of value stream mapping. International Journal of Production Research, 55(13), 3906–3928. https://doi.org/10.1080/00207543.2017.1311031
Soliman, E., Alrasheed, K. A., Alghanim, S., & Morsi, E. (2025). Integrating risk management and earned value framework to detect early warning signs – Case study. Journal of Engineering Research, 13(3), 2109–2116. https://doi.org/10.1016/j.jer.2024.05.029
Sreram, P. K., & Thomas, A. (2026). A discrete event simulation-based value stream mapping framework to support digital lean construction. Engineering, Construction and Architectural Management, 33(2), 1173–1193. https://doi.org/10.1108/ECAM-02-2025-0311
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Ifan Ariosandi, Oki Setyandito , Tota Pirdo Kasih

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International (CC-BY-SA). that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.